Power outages in Papua New Guinea’s three main grids the result of inadequate maintenance, not installed capacity: review

Welcome,

An analysis of Papua New Guinea’s three main power grids has revealed that inadequate maintenance of plants and the transmission lines is the primary cause of frequent power outages, according to a review conducting by London-based consultants, Economic Consulting Associates. The review also comes with some recommendations.

The Yonki hydropower facility in Morobe Province

The Yonki hydropower facility in Morobe Province, which is about to be expanded to boost generation capacity by 194%.

In a report prepared for state utility PNG Power Ltd, Kumul Consolidated Holdings Ltd, and the International Finance Corporation (IFC), the consultants analysed capacity, demand, and constraints facing the Port Moresby, Ramu and Gazelle Peninsula grids.

They also developed an action plan, outlining the priorities, sequencing and investment needs for the three grids over the next 15 years, with an emphasis on the short term (the first five-to-ten years).

‘The key issue is that the power cannot be delivered to the consumer in a reliable way, due to poor availability of generating assets and deficiencies in the maintenance and operation of the transmission grids’

The report, presented to a workshop of industry executives and government representatives in December in Port Moresby, calls for ‘a strenuous effort’ over the next two years to ensure the grids meet internationally accepted sector benchmarks.

The IFC's Gavin Murray

The IFC’s Gavin Murray

‘Basically, the review concluded that there is sufficient existing generating capacity within each of the grids to meet current demand,’ the IFC’s Country Manager, Gavin Murray, tells Business Advantage PNG.

‘The key issue is that the power cannot be delivered to the consumer in a reliable way, due to poor availability of generating assets and deficiencies in the maintenance and operation of the transmission grids.’

Story continues after advertisment...

Pipes

The report notes there is a high proportion of ageing infrastructure within the grids but that reliability of even the newer investments within the grid is considered poor against international benchmarks, because the system is not being maintained to ensure reliability of supply.

‘In plumbing terms, as the pipes get older, you have more leakage, you have more breakages, which reduces efficiency of supply, even if you have sufficient water, and that’s effectively what’s happening within the three grids to various degrees.’

While it was difficult to put a price on fixing the transmission and network issues, Murray says, it is estimated to run into the ‘hundreds of millions of Kina’.

Focus

Murray points out while there are ‘good competent people in PNG Power who understand what needs to be done’, they are distracted ‘by competing priorities or other imperatives’.

‘In plumbing terms, as the pipes get older, you have more leakage, you have more breakages which reduces efficiency of supply, even if you have sufficient water, and that’s effectively what’s happening within the three grids to various degrees.’

‘They clearly understand the need to focus on the network, to focus on upgrading their operating systems, and maintaining their assets and capital investments to deliver on what are reasonable expectations of both their customers and owners.

‘But clearly that’s not well understood or accepted by some of their key stakeholders who want available resources focused on expanding generating capacity and the grid network—often considered the “sexy stuff” that interests politicians and government.

‘And that’s the challenge really: to facilitate PNG Power to be able to get on and do what they need to do.

‘Hence the development of the Action Plan, while holding them to account against a set of transparent management and operating performance criteria.’

Forecast demand

The consultants say it is difficult to forecast demand, which is linked to economic growth, future grid extensions, and proposed new projects, noting ‘a single mine connecting to PPL’s grid could potentially double or even triple load on the system overnight’.

… while there are ‘good competent people in PNG Power who understand what needs to be done’, they are distracted ‘by competing priorities or other imperatives … And that’s the challenge really-to facilitate PNG Power to be able to get on and do what they need to do.’

They conclude, however, that demand for the Port Moresby grid could increase by between 3% and 6%; the Ramu grid by between 2.5% and 5% and the Gazelle grid by between 1% and 3.5% over the next 10 years.

Private sector involvement

‘We need to accept that any future power generation should be developed by the private sector, rather than by PNG Power, as independent power producers.

‘That requires the government to think about how it attracts the best partners with the necessary track record and financial backing to be able to put these projects into play quickly, on the right contractual terms.’

‘It’s probably time, under the new Kumul structure, for PNG Power to move towards a corporatised, commercially-governed operating model and to restructure themselves into those three stand-alone business divisions.’

‘It’s something that’s now well accepted throughout the rest of the developed world and there are organisations out there who do this for a living. So, let’s use that infrastructure development model but through open and competitive processes to get the best deal for PNG,’ says Murray.

PNG Power restructure?

‘Further down the track, you can then look at how to get private sector involvement in transmission investments but that will require further liberalisation of the energy sector in PNG.’

PNG Power has been contemplating whether it should restructure along the lines of the three different businesses that it operates: generation, transmission and retail.

‘It’s probably time, under the new Kumul structure, for PNG Power to move towards a corporatised, commercially-governed operating model and to restructure themselves into those three stand-alone business divisions,’ Murray concludes.

Comments

  1. Israel Izenberg says

    I read the report with a mixed view. I agree that the power generating and distributing infrastructure lacks adequate timely maintenance which is a key attribute to degrading power services. But the fact that the consultants and those advocating private partnership or outright sale of the power infrastructure must know is that there are two major constraints facing PPL now apart from other minor distractions. These two constraints are: (1) inadequate government funding support for PNG Power and (2) a lot of rate payers don’t pay up their bills including an increase in power theft. PNG Power can adapt for the better if these two constraints are mitigated. Even splitting the company into three business units would not help PNG Power and government business. It would only create avenues for private ownership and perhaps high cost of power in the future.

  2. Thanks for the information concerning the reasons for the unreliable services, not that it’s surprising. Much of our existing government services and especially infrastructure have reached their expiration date with no plans to change or upgrade anytime soon, and yet they’re still expected to perform up to standard? That goes for human resources as well. It’s good to see international consultants coming in and making honest assessments of our SOE’s and what is required to improve them but as with everything else, we need to ensure it get done and by the right people. I agree with what was stated about the need for an open and competitive process to ensure the best is acquired, and with no political interfering or influence in the process. I can only pray this happens, but God knows how difficult it is to challenge and alter the status quo. Pleading for divine intervention…

    • Lindah Wesley says

      Apart from the above mentioned outages and constraints experience d by pngpower are there any more reason s why pngpower is not taking of in terms of its performances

  3. The linemen (who provide us with excellent support to restore supply in all weather and at any hour) have been telling me this for more than 10 years now.

Leave a Reply