A big plan to connect 70 per cent of Papua New Guinea to power by 2030 grabbed headlines. Delivering is the true challenge, explains Shane McLeod, research associate working with the Lowy Institute’s Australia-PNG Network.

Transmission lines installation in Kimbe, West New Britain. Credit: ABD/Flicker

Getting the leaders of five Asia-Pacific nations together for the photograph amidst the tumult of a APEC Leaders Summit in Port Moresby last November was a triumph of logistics.

But the last-minute scramble to get an upside down Papua New Guinea flag turned the right way up was maybe a sign of how quickly the PNG Electrification Partnership had come together.

The unspoken theme of the summit in Port Moresby had become how the ‘traditional’ powers in the Pacific could counter the growing presence and prominence of the emerging regional superpower: China.

The ‘traditional’ partners, led by Australia, needed something to demonstrate their continued relevance and relationship.

And the Electrification Partnership would be how they did it.

Electrification partnership

Yonki Dam project. Credit: PNG Power Ltd

Australia, along with the United States, New Zealand and Japan joined together to pledge they would help PNG meet its target of connecting 70 per cent of the country to electricity by 2030. It checked all the boxes: infrastructure, alliances and meaningful development outcomes.

Story continues after advertisment...

But four months on from the announcement, there’s uncertainty about what the Partnership means—and whether it can realise the ambitious goal of connecting nearly two-thirds of PNG’s population to electricity within the next decade.

Per capita, PNG is one of the world’s least-electrified countries. Just 13 per cent of the country’s eight million citizens have the power on. Most of them are in urban centres.

Lifting electricity supply has been identified as one of the key goals of the country’s Development Strategic Plan. Launched in 2010, the policy called for 70 per cent of the country’s people to be connected to electricity within 20 years. It projected that achieving the 2030 goal would lift gross national income by 12 per cent and GDP by 10 per cent.

But progress has been extremely limited—with a lack of funding, a complicated government and regulatory regime, and the difficulty of delivering services in one of the world’s most rugged and diverse countries, where four in five people live in traditional rural settings.

That’s before you factor in the complexity of negotiating with landowners for access for infrastructure; and the question of how to get potential electricity customers—who live outside the formal economy—to pay for their electricity to make the supply sustainable. Access to electricity is estimated to have grown by only 3.4 per cent in total since that 2010 goal was set. An interim target of lifting total access to 33% as part of the 2022 Medium Term Development Plan is well behind schedule.

That’s where Australia and its partners in the PNG Electrification Partnership come in.

The agreement was heralded as a ‘true partnership’ between PNG and its key partners; aligned with PNG’s plans and priorities and delivered through existing structures—including the existing state-owned provider, PNG Power Limited.

Chinese involvement

PNG’s government wants to develop the Ramu-2 hydroelectric project in the Eastern Highlands—its output is slated to be prioritised for big mining developments in neighbouring Morobe and Madang provinces. Work is slated to commence soon led by a consortium headed by the Shenzen Energy Group from China, to be delivered under a Public-Private Partnership over 25 years in a deal reported to be worth up to US$2 billion (K6.75 billion).

The Asian Development Bank has been the biggest international donor working with PNG to achieve its long-term electrification goals. Through programs targeting electricity supply in regional towns, the national capital and provincial centres, it has been working with PNG Power on designing and funding upgrades tied to social outcomes.

‘For villages with populations of less than 2,000 people, unless they are within five kilometres of an existing power line, it is cheaper to use local power generation rather than a grid connection.’

It’s feasible that some of that work could be taken up by the PNG Electrification Partnership and its members.

But large-scale investments may not be the cheapest or most effective pathway to achieving PNG’s 2030 electrification goals. A 2015 report prepared for ANZ Bank considers the challenge by bringing in most recent understandings of renewable, off-grid and micro-generation technologies.

Remote population centres

Grid extension for remote villages in PNG. Credit: ANZ Bank/Port Jackson Partners

Author Grant Mitchell points out that because 80 per cent of PNG’s population lives in rural areas, the big hurdle in electrification will be getting power to remote population centres—villages that might have just a few hundred people.

Fully 65 per cent of the population in those areas will need access to power if the 2030 goal is to be met.

But as new stand-alone generation alternatives become available, the case for extending PNG’s electricity network’s poles and wires weakens. And the economic case for big scale investments in big generation projects—like multi-billion-dollar hydroelectric dams—might also be questionable.

Mitchell’s analysis suggests that for villages with populations of less than 2,000 people, unless they are within five kilometres of an existing power line, it is cheaper to use local power generation rather than a grid connection. Larger provincial towns—he uses the example of Wewak—would need populations of more than 100,000 people or be closer than 50 kilometres to the grid to make the numbers stack up.

Mitchell’s report also contemplates the big infrastructure investments on the generation side that will be needed to meet an estimated tripling of national electricity demand.

Mitchell says it is only at large scale that expensive investments such as hydroelectric dams become cost-competitive against other generation technologies.

The monopoly state-owned provider, PNG Power, will be central to whatever happens. Its Acting Managing Director Carolyn Blacklock has been positive about what the Partnership will mean, and how it can help her organisation to lock in financing for big investments.

And the potential investors (Australia, the US, New Zealand and Japan) need to think about what they want to do to help PNG to achieve its electrification goals.

Having committed themselves so publicly to the big ambitious electrification goal, they have limited time to get started if they want to reach the target.

Shane McLeod is a Research Associate working with the Lowy Institute’s Australia-PNG Network. This is an edited version of an article first published on the Lowy Institute’s Interpreter blog. 